Petrochemicals and chemical production
1
Taraz Chemical Park Special Economic Zone Project
Client:
JSC "Management Company SEZ "Chemical Park Taraz"
Stage:
Project, Working Documentation and Author's supervision
Year:
2012-2014
Project highlights
Within the framework of the Taraz Chemical Park project, work was carried out on the design, development of working documentation and supervision of the infrastructure facilities of a large industrial center. The territory of the FEZ unites chemical industries, which are managed by a single management company. The main task was to provide comprehensive engineering support, which made it possible to create a modern industrial complex that promotes the development of the chemical industry and attracts investment to the region.

The aim of the project is to create a modern infrastructure and organizational structure of the Taraz Chemical Park special economic zone to form an effective industrial center that ensures:
  • the development of the chemical industry.;
  • attracting investments;
  • increasing the economic potential of the region.
2
The project of the hydrogen production Pavlodar Petochemical Plant
Client:
KG Process Innovations s.r.o. (Czech Republic)
Stage:
Working Project (Adaptation)
Year:
2006
Project highlights
Hydrogen production plant at Pavlodar Petrochemical Plant
As part of the project, work was carried out to adapt the project documentation developed by the Swiss company Koch-Glitsch to the requirements of the Republic of Kazakhstan.
The main objectives of the project:
  • correct adaptation of foreign project documentation in accordance with national regulations and standards;
  • coordination of design decisions with government and supervisory authorities;
  • ensuring the reliability and compliance of the installation with industrial safety requirements.

Project partner: Koch-Glitsch (Switzerland).
The aim of the project is to provide the plant with the necessary hydrogen for hydrotreating processes, which made it possible to produce fuel that meets international environmental standards Euro-3 and Euro-4, as well as to increase the depth of oil refining to 80-85%.
The project is of strategic importance for improving the quality of petroleum products and strengthening Kazakhstan's position in the fuel and energy complex market.
3
Construction of a natural gas liquefaction plant with a maximum consumption of 1,000 thousand nm3/day in Panfilovsky district of Zhetysu region
Client:
Silk Way Energy LLP
Stage:
Design
Year:
2024
Project highlights
Liquefied Natural Gas (LNG) Production Plant
Location: Zhetysu region, Panfilovsky district
Production capacity: 1 million m3/day
Building area: 474 ha
Project cost: USD 273 million
The company is focused on solving strategically important tasks — gasification of remote areas of the Republic of Kazakhstan, as well as the development of the country's export potential. The bulk of the products — up to 85% — will be supplied to the international market, primarily to China.

The implementation of the project will allow:
  • ensure access to natural gas in remote regions of Kazakhstan;
  • expand the export opportunities of the domestic gas industry;
  • to increase the energy security and economic potential of the region.
Project

Stage

Year

Provision of engineering services for development of the project “Construction of a natural gas liquefaction plant with a maximum feed gas consumption of 1,000 thousand Nm³/day in Panfilov District, Zhetysu Region.”
Client: “SILK WAY ENERGY LTD” Private Company.

Project

2024

Development of design and estimate documentation for the project “Construction of Multi-Fuel Filling Station No. 23, at 1/2 A. Orazbayeva St., Zhangala Village, Zhangalinsky Rural District, West Kazakhstan Region.”

Working Project

2021

Development of design and estimate documentation for the project “Construction of Multi-Fuel Filling Station No. 21, at 40v Tauman Amandosov St., Atyrau.”

Working Project

2021

Provision of engineering services for development of projects at the Kozha Yuzhny field.
Client: KSK Petroleum Ltd LLP (Green Production LLP).

Engineering services

2020

Design of infrastructure facilities for the Taraz Chemical park SEZ (railway facilities, water pipeline, and internal infrastructure).
Client: Management Company of the Khimpark Taraz SEZ JSC.

Working Project

2019

Provision of engineering services for works at the Kozha Yuzhny field located in Atyrau Region, Republic of Kazakhstan.
Client: YUVINAL LLP.

Engineering services

2019

Design of infrastructure facilities for the Taraz Chemical park SEZ.
Client: Management Company of the Taraz Chemical park SEZ JSC.

Working Project

2019

Author’s supervision of construction and installation works for the project “Increase of production capacity at Site No. 2, Tortkudyk, Moiynkum deposit, with выделение into a separate construction phase of ammonia water storage facilities in Sozak District, South Kazakhstan Region.”
Client: JV KATCO LLP.

Author’s supervision

2017

Associated petroleum gas processing development program for the Khairkeldy North field (2017–2019).

Associated petroleum gas utilization program

2017

Author’s supervision for the working design “Reconstruction of hydraulic distribution networks for process solutions at the Moiynkum deposit. Development of pipeline protection measures” (SIP-66-1, Pumping Station, 1st start-up complex).

Author’s supervision

2017

Development of design and estimate documentation for Beibars Gaz Group of Companies; author’s supervision during construction for the project “Tie-in of gas wells No. 30 and 7R.”

Author’s supervision

2017

Author’s supervision of construction and installation works for the project “Increase of production capacity at Site No. 2, Tortkudyk, Moiynkum deposit, with выделение into a separate construction phase of ammonia water storage facilities in Sozak District, South Kazakhstan Region.”

Author’s supervision

2016

Author’s supervision for the working design “Reconstruction of hydraulic distribution networks for process solutions at the Moiynkum deposit. Development of pipeline protection measures” (SIP-66-1, Pumping Station, 1st start-up complex).
Client: JV KATCO LLP.

Author’s supervision

2016

SIP-66-1: “Reconstruction of hydraulic distribution networks for process solutions at the Moiynkum deposit. Development of pipeline protection measures.”
Client: JV KATCO LLP.
Working Project
2016
Development of as-built drawings for the project “Reconstruction of Section 500 of the CППР at Site No. 2, Tortkudyk, Moiynkum deposit.”
Client: JV KATCO LLP.
Working Project
2016
Revision of the working design “SAR-34. Construction of hydraulic pipeline networks for distribution of process solutions to TNU 15–18 blocks at Site No. 2, Tortkudyk Severny, Moiynkum deposit.”
Client: JV KATCO LLP.
Working Project
2016
Revision of the working design “Construction of a well testing and oil storage unit at the Sarybulak field.”
Client: Tarbagatai-Munai LLP.
Working Project
2016
Privacy Policy
KATEK LLP Design and Engineering Company
© 2025 All rights reserved.
katek@katek.kz
tel: +7 (727) 241 13 77
tel: +7 (727) 241 13 88
050010, Republic of Kazakhstan
Almaty, Snaipersky Lane, 4